| Grading and Excavation |
February-March 2008 |
| Concrete Foundation Piers |
March-April |
| Structural Steel Erection |
June-July |
| Place Concrete @ Slab on Grade |
June |
| Place Concrete @ Main Floor |
July |
| Place Concrete @ 2nd Floor |
July |
| Place Concrete @ 3rd Floor |
July |
| Place Concrete @ 4tth Floor |
August |
| Exterior Skin (Framing/Windows/Plaster) |
August 2008-March 2009 |
| Concrete at Interior Courtyard |
January 09 |
| Setting Main Dining Kitchen Equipment |
January-February 2009 |
| Site Concrete/Landscaping |
April-May 2009 |
| Building ready for occupancy |
May 2009 |